Saudi Water Bottler: 60,000 BPH Line from Cold Start in 7 Months

Greenfield 60,000 BPH water bottling line: blowing, filling, capping, labeling, shrink-wrapping and palletizing. Cold-start to first commercial sale in 7 months (vs 14-month industry average). OEE run

ClientConfidential (top-3 Saudi Arabian bottled water producer)RegionSaudi ArabiaConfidentialNDA on file
SA

Region

Saudi Arabia

60,000 BPH · 7 months

The project

Water bottling line installation
60,000 BPH line at a Saudi water bottling plant (2025)

The challenge

A top-3 Saudi Arabian bottled water producer broke ground on a greenfield facility in Riyadh. The line had to produce 60,000 BPH (500 ml format) for the Hajj season — a hard deadline 7 months out, since missing it would mean losing a full year of seasonal demand.

Scope: complete line from PET preform supply through palletized finished goods, including all interconnecting conveyors, CIP system, quality-control equipment and regulatory documentation for SFDA (Saudi FDA) approval.

Our approach

We assigned a 6-person project team (mechanical, electrical, controls, process, validation and project management) on day 1. The team worked from a shared project schedule with weekly customer check-ins.

  • Month 1-4: Engineering, manufacturing, in-house FAT for all machines
  • Month 5: Sea freight + on-site installation (all 6 ApexForge engineers on site for 8 weeks)
  • Month 6: Commissioning and operator training (24 operators across 3 shifts)
  • Month 7: SFDA validation, IQ/OQ/PQ documentation, first commercial sale

Results after 6 months of production

  • On-time delivery: First commercial sale exactly 7 months after kickoff (vs 14-month industry average for greenfield lines)
  • OEE: 88% after 6 months (industry target for greenfield lines is 75% in year 1)
  • Quality: 99.97% conforming product at end-of-line (3 ppm defect rate)
  • Energy: 18% below design target due to servo-driven conveyors and VFD-controlled pumps
  • Volume grown: Customer added a second identical line from us in month 9

What made the difference

  1. Integrated project team: One project manager, one schedule, one set of milestones — not 6 separate vendor relationships the customer had to coordinate
  2. In-house FAT (Factory Acceptance Testing): Every machine was assembled, tested with real PET preforms, and documented at our Hangzhou facility before shipment. On-site surprises minimized.
  3. Regional service hub: Our Dubai hub (4-hour flight from Riyadh) provided spare parts, warranty support and additional operator training for the customer's second line

Reviewed and confirmed by the customer and the ApexForge project team before publication.